Start here

The essentials

This brief sets the Cabinet's approval of Bharatmala Phase I in October 2017 against the Ministry's own answer to Parliament of 22 July 2026 and against CAG's audit of Phase I. On Saturday 24 October 2026 the programme completes nine years since the Cabinet approved it.

Not awarded

On the Ministry's answer of 22 July 2026, projects had been awarded for 26,425 km of the 34,800 km approved. That leaves 8,375 km, which is 24.1 per cent, not awarded under Phase I. The same answer says that new sanctions of projects under Phase I have been discontinued since November 2023. The Ministry told the Lok Sabha on 5 February 2026 that Bharatmala "has been discontinued since November 2023 with only awarded projects being taken up for completion".

Source: Rajya Sabha Unstarred Question No. 414, 'Implementation of Bharatmala Pariyojana', answered on 22 July 2026 ; Ministry of Road Transport and Highways, written reply in the Rajya Sabha, released by PIB on 18 December 2017 (Release ID 174465) ; Lok Sabha Unstarred Question No. 1025, 'Completion of Projects under Bharatmala Phase-I', answered on 5 February 2026 .

Not built

The Ministry told the Rajya Sabha that 22,709 km had been constructed up to May 2026, which is 65.3 per cent of the approved length. So 12,091 km of the length approved in 2017 had not been built by May 2026, although the five years that the Ministry gave Parliament ended with 2021-22.

Source: Rajya Sabha Unstarred Question No. 414, 'Implementation of Bharatmala Pariyojana', answered on 22 July 2026 ; Ministry of Road Transport and Highways, written reply in the Rajya Sabha, released by PIB on 18 December 2017 (Release ID 174465) .

CAG's count

In its Report No. 19 of 2023, the Comptroller and Auditor General of India counted the progress of Phase I up to 31 March 2023, after those five years had ended. CAG found that 13,499 km had been completed by then, which was only 38.79 per cent of the approved length.

Source: CAG Report No. 19 of 2023, Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana, listed on 10 August 2023 .

The cost

On CAG's own count, the projects awarded up to 31 March 2023 carried a sanctioned cost of Rs 32.17 crore per km, while the Cabinet's approval worked out to Rs 15.37 crore per km. CAG also found that 158.24 per cent of the approved outlay had been sanctioned when only 75.62 per cent of the length had been awarded. The Ministry itself told the Lok Sabha on 31 July 2025 that projects covering 26,425 km "were awarded at a cost of about Rs 8.53 lakh Crore", against the Rs 5.35 lakh crore estimated in 2017 for all 34,800 km.

Source: CAG Report No. 19 of 2023, Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana, listed on 10 August 2023 ; Lok Sabha Unstarred Question No. 1975, 'Cost Escalation under Bharatmala Pariyojana', answered on 31 July 2025 .

01 / The evidence

The promise of 24 October 2017

The Ministry of Road Transport and Highways described the approval in a written reply in the Rajya Sabha, which the Press Information Bureau released on 18 December 2017. The reply named the date, the length and the time for the work, in the words below.

WhereThe words
Ministry's written reply, released by PIB on 18 December 2017, first paragraphThe Cabinet has accorded approval to the investment proposal for the programme Bharatmala Pariyojana (BMP) Phase I on 24 th October 2017 for 34,800 km
The same replyThe above is to be implemented over a period of five years i.e. 2017-18 to 2021-22.
Answer to Rajya Sabha Unstarred Question No. 414, 22 July 2026, page 1covering a length of 34,800 km across the Country at an estimated outlay of Rs. 5,35,000 Crore

The outlay of Rs 5,35,000 crore was approved for the whole 34,800 km, as the Ministry's answer of 22 July 2026 repeats.

Source: Ministry of Road Transport and Highways, written reply in the Rajya Sabha, released by PIB on 18 December 2017 (Release ID 174465) ; Rajya Sabha Unstarred Question No. 414, 'Implementation of Bharatmala Pariyojana', answered on 22 July 2026 .

02 / The evidence

The approved length, awarded and built

The Ministry's answer of 22 July 2026 sets the length awarded and the length built against the 34,800 km the Cabinet approved. Both counts run to May 2026. The office's arithmetic on that answer gives the two gaps, which the chart shows in red.

Bharatmala Phase I: the approved length, awarded and constructedBharatmala Phase I: approved, awarded, constructedKilometres of national highwayApproved by the Cabinet24 October 2017Approved by the Cabinet: 34,800 km34,800 kmAwardedthe Ministry's count, to May 2026Awarded: 26,425 km, 75.9 per cent26,425 km, 75.9 per centConstructedthe Ministry's count, up to May 2026Constructed: 22,709 km, 65.3 per cent22,709 km, 65.3 per centNot awardedoffice arithmetic, answer of 22 July 2026Not awarded: 8,375 km, 24.1 per cent8,375 km, 24.1 per centNot constructedoffice arithmetic, up to May 2026Not constructed: 12,091 km12,091 kmSource: Ministry of Road Transport and Highways, answer to Rajya Sabha Unstarred Question No. 414 of 22 July2026 and its annexure; the approval, PIB, 18 December 2017.
Bharatmala Phase I: approved, awarded, constructed
Kilometres of national highway
Bharatmala Phase I: the approved length, awarded and constructedApproved by theCabinet24 October 201734,800 kmAwardedthe Ministry's count, toMay 202626,425 km, 75.9per centConstructedthe Ministry's count, upto May 202622,709 km, 65.3 percentNot awardedoffice arithmetic, answerof 22 July 20268,375 km, 24.1 per centNot constructedoffice arithmetic, up toMay 202612,091 km
Source: Ministry of Road Transport and Highways, answer to Rajya Sabha Unstarred Question No. 414 of 22 July 2026 and its annexure; the approval, PIB, 18 December 2017.
The chart means that, on the Ministry's own answer, nearly a quarter of the approved highway had not been awarded under the programme, and that more than a third of it had not been built.
FigureWhat it countsAs ofWhere
34,800 kmLength the Cabinet approved for Phase I24 October 2017PIB, 18 December 2017
26,425 kmLength awarded under Phase IMay 2026RS USQ 414, page 1 and annexure
22,709 kmLength constructed, 65.3 per cent of the approved lengthMay 2026RS USQ 414, page 1
8,375 kmApproved length not awarded, 24.1 per cent22 July 2026Office arithmetic on RS USQ 414
12,091 kmApproved length not constructedMay 2026Office arithmetic on RS USQ 414

Source: Rajya Sabha Unstarred Question No. 414, 'Implementation of Bharatmala Pariyojana', answered on 22 July 2026 ; Ministry of Road Transport and Highways, written reply in the Rajya Sabha, released by PIB on 18 December 2017 (Release ID 174465) .

03 / The evidence

What CAG found by 31 March 2023

CAG's Report No. 19 of 2023 gives the position of Phase I up to 31 March 2023. By that date 26,316 km had been awarded, which was 75.62 per cent of the approved length. Only 13,499 km had been completed, which was 38.79 per cent.

What CAG found by 31 March 2023What CAG found by 31 March 2023Kilometres of national highway under Phase IApproved by the Cabinet24 October 2017Approved by the Cabinet: 34,800 km34,800 kmAwardedCAG's count, up to 31 March 2023Awarded: 26,316 km, 75.62 per cent26,316 km, 75.62 per centCompletedCAG's count, up to 31 March 2023Completed: 13,499 km, 38.79 per cent13,499 km, 38.79 per centSource: CAG Report No. 19 of 2023, listed on 10 August 2023, pages iii, vi and 6.
What CAG found by 31 March 2023
Kilometres of national highway under Phase I
What CAG found by 31 March 2023Approved by theCabinet24 October 201734,800 kmAwardedCAG's count, up to 31March 202326,316 km, 75.62per centCompletedCAG's count, up to 31March 202313,499 km, 38.79 per cent
Source: CAG Report No. 19 of 2023, listed on 10 August 2023, pages iii, vi and 6.
The chart means that, once the five years the Ministry gave Parliament had passed, CAG found well under half of the approved length complete. CAG's count and the Ministry's count were made on different dates, so each figure in this brief carries its own date.
FigureWhat CAG countedAs ofWhere
26,316 kmLength awarded, 75.62 per cent of the approved length31 March 2023CAG, page iii
13,499 kmLength completed, 38.79 per cent of the approved length31 March 2023CAG, page 6

Source: CAG Report No. 19 of 2023, Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana, listed on 10 August 2023 .

04 / The evidence

The cost per kilometre, on CAG's own count

CAG set the sanctioned cost of the projects against the cost the Cabinet approved, and both comparisons below are its own. The sanctioned cost is the cost fixed for each project when it was cleared. The civil cost is the cost of the construction work alone.

Cost per kilometre, approved and sanctioned, on CAG's own countCost per kilometre, on CAG's own countRs crore per km of national highwayApproved by the Cabinet, October 2017Sanctioned, up to 31 March 202305101520253035Whole cost per km, Approved by the Cabinet, October 2017: Rs 15.37 crore per km15.37Whole cost per km, Sanctioned, up to 31 March 2023: Rs 32.17 crore per km32.17Whole cost per kmCivil cost per km, Approved by the Cabinet, October 2017: Rs 13.98 crore per km13.98Civil cost per km, Sanctioned, up to 31 March 2023: Rs 23.89 crore per km23.89Civil cost per kmSource: CAG Report No. 19 of 2023, listed on 10 August 2023, pages iii, vi and 6.
Cost per kilometre, on CAG's own count
Rs crore per km of national highway
Approved by the Cabinet, October 2017Sanctioned, up to 31 March 2023
Cost per kilometre, approved and sanctioned, on CAG's own count0510152025303515.3732.17Whole cost per km13.9823.89Civil cost per km
Source: CAG Report No. 19 of 2023, listed on 10 August 2023, pages iii, vi and 6.
The chart means that each kilometre awarded up to 31 March 2023 was sanctioned at more than twice the cost per kilometre that the Cabinet approved. The construction work alone was sanctioned at Rs 23.89 crore per km, against Rs 13.98 crore per km approved.
MeasureApproved by the CabinetSanctioned, up to 31 March 2023Where
Whole cost per kmRs 15.37 crore per kmRs 32.17 crore per kmCAG, page iii
Civil cost per kmRs 13.98 crore per kmRs 23.89 crore per kmCAG, page vi
Whole cost, in totalRs 5,35,000 crore for 34,800 kmRs 8,46,588 crore for 26,316 kmCAG, page iii

CAG put the result in these words: "Upto 31 March 2023, when only 75.62 per cent of CCEA approved length has been awarded, 158.24 per cent of CCEA approved financial outlay has already been sanctioned." CCEA is the Cabinet Committee on Economic Affairs, which approved Phase I.

Source: CAG Report No. 19 of 2023, Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana, listed on 10 August 2023 .

05 / The evidence

Nine years, date by date

The dates below come from the Government's own record. Each line names the document in which the Government or its auditor said it.

DateWhat happenedWhere it is recorded
24 October 2017The Cabinet approves 34,800 km of national highways under Bharatmala Phase I.PIB, 18 December 2017
18 December 2017The Ministry tells the Rajya Sabha that the work is to be done over five years, from 2017-18 to 2021-22.PIB, 18 December 2017
31 March 2023CAG counts 26,316 km awarded and 13,499 km completed.CAG Report No. 19 of 2023
November 2023New sanctions of projects under Phase I are discontinued, as the Ministry later tells the Rajya Sabha.RS USQ 414
May 2026The Ministry counts 26,425 km awarded and 22,709 km constructed.RS USQ 414
22 July 2026The Ministry answers the Rajya Sabha, and 8,375 km of the approved length has not been awarded.RS USQ 414
24 October 2026Nine years pass since the Cabinet's approval.The date of approval

Nine years after the approval, the Government's own answer to Parliament shows that close to a quarter of the highway it approved in 2017 had not been awarded under the programme, and that more than a third of it had not been built.

Source: Ministry of Road Transport and Highways, written reply in the Rajya Sabha, released by PIB on 18 December 2017 (Release ID 174465) ; Rajya Sabha Unstarred Question No. 414, 'Implementation of Bharatmala Pariyojana', answered on 22 July 2026 ; CAG Report No. 19 of 2023, Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana, listed on 10 August 2023 ; Lok Sabha Unstarred Question No. 1975, 'Cost Escalation under Bharatmala Pariyojana', answered on 31 July 2025 ; Lok Sabha Unstarred Question No. 1025, 'Completion of Projects under Bharatmala Phase-I', answered on 5 February 2026 .

Terms, explained

Bharatmala Pariyojana Phase I
It is the first phase of the Union Government's highway programme, which the Cabinet approved on 24 October 2017 for 34,800 km of national highways.
Awarded
A stretch of highway is awarded when the agency in charge gives the contract to build it. In this brief, the length not awarded is the part of the approved length that the Ministry's answer does not show as awarded under Phase I.
Constructed
It is the length that the Ministry reports as built.
Outlay
It is the money that the Cabinet approved for the programme, which was Rs 5,35,000 crore for the whole 34,800 km.
Sanctioned cost
It is the cost fixed for each project when the project was cleared.
Civil cost
It is the cost of the construction work alone, which leaves out the cost of land and other work before building.
CAG
The Comptroller and Auditor General of India audits the accounts of the Union Government and reports to Parliament.
CCEA
The Cabinet Committee on Economic Affairs is the committee of the Union Cabinet that approved Phase I.
Keep the evidence

Downloads for readers and the press

Sources & method

Every figure in this brief comes from five official documents. The first is the Ministry's written reply of 18 December 2017, which the Press Information Bureau released. The second is the Ministry's answer to Rajya Sabha Unstarred Question No. 414 of 22 July 2026, and the third is CAG's Report No. 19 of 2023. The last two are the Ministry's answers in the Lok Sabha of 31 July 2025 and 5 February 2026. Each was read in a saved copy, and every quotation was found again, word for word, before this brief was built.

Five figures are the office's own arithmetic on the answer of 22 July 2026, and each uses two figures that stand in one table of that answer. The length not awarded is 34,800 km less 26,425 km, which is 8,375 km, or 24.1 per cent. The length built, 22,709 km, is 65.3 per cent of the approved length, which leaves 12,091 km not built. The length awarded is 75.9 per cent of the approved length.

CAG's figures are printed as CAG printed them, and they are counted up to 31 March 2023. The Ministry's lengths are counted up to May 2026, and its cost figure is the one it gave the Lok Sabha on 31 July 2025. The two counts were made on different dates, so this brief gives each figure its own date and does not join them into one series.

Every share that the office worked out is rounded once, to one decimal, from the unrounded result.

  1. Ministry of Road Transport and Highways, written reply in the Rajya Sabha, released by PIB on 18 December 2017 (Release ID 174465) .
  2. Rajya Sabha Unstarred Question No. 414, 'Implementation of Bharatmala Pariyojana', answered on 22 July 2026 .
  3. CAG Report No. 19 of 2023, Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana, listed on 10 August 2023 .
  4. Lok Sabha Unstarred Question No. 1975, 'Cost Escalation under Bharatmala Pariyojana', answered on 31 July 2025 .
  5. Lok Sabha Unstarred Question No. 1025, 'Completion of Projects under Bharatmala Phase-I', answered on 5 February 2026 .